On track, two asks

Atlas Programme · May steering update. A status deck is a decision instrument, not a diary: what moved, what we are watching, and the decisions we need while there is still time to act. This deck is built that way — and shows you how.

02 This period

On track overall — the UAT slip is contained, two decisions due today

Scope On track Schedule Watch Budget On track Risk Watch
Shipped
  • ·Platform build passed integration test
  • ·Enablement wave one trained, 96% attendance
Watching
  • ·Migration dry run waits on the vendor decision
  • ·UAT start slipped two weeks; go-live still holds
Next
  • ·Close the vendor decision, start dry run one
  • ·Sign off UAT scripts with the business leads
02 / 16
03 Workstreams

Three of four workstreams green — migration needs today’s decision

Workstream
Scope
Schedule
Budget
Risk
Trend
Platform build
Data migration
Enablement
Reporting

 on track  ·   watch  ·   at risk  ·  arrow = trend since last steering

03 / 16
04 Milestones

Go-live holds at 28 Nov — UAT absorbs the slip

MilestoneOwnerDueStatus
Design freezeProduct14 MarDone
Platform build completeEngineering30 JunOn track
Migration dry run oneData15 AugAt risk
UAT startBusiness29 SepSlipped 2 wks
Go-liveProgramme28 NovHolds

Status at 31 May · plan of record v3.

04 / 16
05 Risks

Every open risk carries an owner and a date

RiskImpact if it landsMitigationOwnerSeverity
Vendor capacity in Q3Dry run slips past AugustSecond vendor pre-qualified; decision todayPMOHigh
Legacy data qualityReconciliation re-work in UATProfiling done; cleanup sprint in JuneData leadMedium
Key-person dependencyIntegration knowledge in one headPairing since May; runbook by 30 JunEng. managerMedium

Full register in the appendix pack · reviewed weekly.

05 / 16
06 Decisions

Two decisions today keep November safe

Decision 1

Approve the migration vendor

The €80k contract closes the dry-run capacity gap; two weeks of onboarding are already in the plan.

Decide by 7 Jun · sponsor: CFO

Decision 2

Release one data engineer

Four weeks from Team B unblocks the reconciliation scripts before the cleanup sprint ends.

Decide by 14 Jun · sponsor: CTO

If either slips

Go-live moves a month — the workplan slide shows the path either way.

06 / 16
07 Part two
Part two

The evidence behind the headline

Numbers, spend, the plan, and what moves next period.

07 / 16
08 The numbers

The programme in three numbers

62%
Scope delivered and accepted.
€1.9m
Spent of the €2.4m budget.
11/14
Milestones hit on their original date.

Programme office, status at 31 May.

08 / 16
09 Budget

Spend tracks plan — €0.2m under, contingency untouched

Cumulative spend runs just under the curve; the gap is timing, not scope.

  • ·Forecast at completion: €2.35m
  • ·Contingency of €150k not drawn
  • ·Vendor contract adds €80k from June

Source: finance actuals to 31 May.

JanMarMay
09 / 16
10 Workplan

The plan to November on one slide

Q1
Q2
Q3
Q4
Platform
build
Build & integrate
Data
migration
Dry runs & cutover
UAT
Scripts & execution
Enablement
Train the regions
Go-live

Programme office · plan of record v3.

10 / 16
11 Next period

What moves before the next steering

Next two weeks

Close the asks

Vendor signed, engineer released, dry-run environment ready.

By next steering

Dry run one

First migration dry run complete; UAT scripts signed off.

The quarter

UAT running

Business testing underway; go/no-go criteria agreed for November.

The focus

Protect the migration critical path — everything else on the plan has slack.

11 / 16
12 Dependencies

Three cross-team needs — one blocked

We needFromByStatus
Security review slotIT Security20 JunRequested
API rate-limit increasePlatform team30 JunAgreed
Anonymised test data setFinance ops15 JunBlocked

Escalation path: programme sponsor → CIO weekly.

12 / 16
13 Changes

Scope changes stay inside contingency

Change requestCostScheduleStatus
CR-11 · Drop the legacy export−€15k±0 weeksApproved
CR-12 · French localisation+€40k±0 weeksIn review
CR-13 · Extra training wave+€20k+1 weekDeclined

Change board of 22 May · net approved to date: +€25k.

13 / 16
14 So what
The habit

A status update is a decision instrument, not a diary. Lead with what changed — and ask early, because bad news does not improve with age.

14 / 16
15 Open canvas

Free canvas — keep the header and footer, then compose any layout you like in this space. Text, boxes, inline SVG, a table or a chart all still convert to native, editable objects.

15 / 16
16 Close
Next steps

Two asks on the table — next steering 25 June

The asks

Vendor approval by 7 Jun; the engineer by 14 Jun.

Between steerings

Weekly one-pager to sponsors; escalations any time.