Warehouse system rollout, reported to the steering group.
Cumulative spend against plan, € thousands, June to October
Every site that went live is picking more accurately and needed no rollback.
Malmö, Aarhus and Tallinn moved on their planned weekends. Support tickets fell back to normal within ten days at each site.
Gdańsk is different: its stock records were kept in two systems for years, and a third of them disagree. Cleansing them is the work that sets the date.
€38,000 from contingency (€172,000 left); all four sites live before peak season.
Decision needed by 24 October
Releases the contingency for two extra integrators.
Scanner firmware and the label printers first.
Cut-over date confirmed or moved, with a reason.